CAL Maritime Dining Hall and Bookstore
School/University
Foundation System
Geologic Hazard(s)
Location
Vallejo, CA
Owner
California Maritime Academy
Geotechnical Engineer
Structural Engineer
General Contractor
Farrell Solves Liquefaction &
Lateral Spread for Cal Maritime
The California Maritime Academy, a California State University campus, sits on the south side of Vallejo and fronts San Pablo Bay near the Carquinez bridge at Morrow Cove. The site served as the ferry terminal up to the 1920’s for the Carquinez strait to Crocket. The site has been filled since the 1920’s to its present state to expand the campus for the growth of the California Maritime Academy. In the late 1990’s, a seismic upgrade project was performed to improve the shoreline against liquefaction and lateral spread, but not in the western portion of the site near the new dining hall.
California Maritime Academy expanded its campus to include a new dining center and renovations to the bookstore in 2012. The new Dining Center features breathtaking, waterfront views from two stories and a mezzanine. The 26,000-square foot Dining Center seats 400 for meals and 272 for banquets.
The subsurface conditions are challenging, Dave Cymanski, GE with KC Engineering, the GEOR, identified undocumented, contaminated, fill over loose sand and soft, compressible bay mud, over bedrock. Geologic hazards include soft, compressible clay, liquefaction and lateral spread with the sloping bedrock toward the bay. KC estimated 1 to 3 inches of static settlement plus 7 to 9 inches of liquefaction settlement could occur during the MCE seismic event (PGA=0.6). The CSU needed a strong foundation and ground improvement system to mitigate settlement from static loads and the liquefaction and lateral spread.
Farrell was selected by McCarthy Building Companies, Inc. and the California State University Chancellors (CSU) to provide a design-build ground improvement solution to mitigate the geologic hazards. The Cal Maritime project is an excellent example of state-of-the-art geotechnical engineering and ground improvement contracting delivered by a design-build contract within the requirements of the current CSU Seismic Policy.
Project Details
KC Engineering recommended stone columns, rammed aggregate piers, soil cement mixing, or compaction grouting. After Farrell’s additional borings, CPTs, and testing, Farrell proposed the Drill Displacement Column™ (DDC) ground improvement method to install strong “composite ground.” DDC can be installed in rocky, colluvium, and fill, unlike an aggregate pier or stone column that requires pre-drilling. DDC were installed to depths of 38 feet into the fill, loose sand layers, bay mud, and bedrock. Farrell worked with KC Engineering, Forell Elsesser, and AMEC (CSU seismic peer review) to design and build DDC for the lateral spread buttress, liquefaction mitigation, and foundation and slab support.
The DDC design had to address structure settlement and liquefaction and lateral spread at the shoreline. AMEC and KC required a psuedo-static slope stability analysis to demonstrate that DDC would mitigate the lateral spread hazard. Due to the soft bay mud and loose sand deposits below the fill, the DDC were designed to provide “composite ground” with increased shear strength thru the lateral spread zone and increased sand density. Lateral spread threshhold displacements from SP117A were used to determine the seismic coefficient (kh). The unimproved condition was computed with kh = 0.2. The “composite ground” has increased stiffness which was modelled with a kh = 0.3. Farrell engineers collaborated with AMEC and KC to refine the psuedo-static model using Slide 6.0. DDC spacing was adjusted, engineered grout mix strengths tested, and Farrell ran the analysis to an acceptable safety factor > 1.1 for the seismic coefficent with a threshold displacement of 5 to 15 cm.
Farrell installed over 500 DDC that ranged in depth from 10 feet to 38 feet. The DDC were advanced with a 165,000 ft-lb drill on a 75 ton LRB 155 piling rig using an 18-inch diameter drill displacement tool. During installation, the drill tool pinged when advancing thru the rocky fill zones at depths of 20 and 25 feet, then it was easy drilling thru the bay mud and lose sand to the claystone bedrock. The DDC process displaced the soil and rocky fill in the ground eliminating drill spoil. After drilling to bedrock, grout was pumped at pressures of 75 to 150 psi (5 to 10 bar) to start the compaction grout process. The replacement volume of grout below the rocky fill was targeted at 1.2x and reached up to 1.5x the neat 18-inch displaced volume. Ground improvement was achieved by the 18 inches of displaced and compacted soil and then the compaction grout effect resulting in strong “composite ground.” The displacement and compaction grout effect raised the site 3 to 5 inches, confirming increased density and improvement. The dining hall opened in October 2013.
2014 Napa Earthquake
About one year after opening on the morning of August 24, 2014, the Napa earthquake (M6.0) was felt 100 miles from the epicenter. The Cal Maritime site sits about 11 miles south of the epicenter. Approximately 1.2 miles south of the site, two seismic stations measured the PGA at the Carquinez Bridge abutments with values of 0.34g and 0.7g with acceleration spikes nearly 1.0g recorded in the Geotechnical Array No. 1 in the north-south direction (GEER 2014). After the earthquake, Farrell performed a site review to assess the structure and butress. Visual inspections showed no ground cracks or signs of lateral spread at the DDC buttress and in service structure condition.
DDC “composite ground” strengthened the site to support the new structure, control static and seismic settlement to less than 1 inch, and mitigated liquefaction and lateral spread during an M6 earthquake. The Cal Maritime Dining Center performance exemplifies Farrell’s motto of Go Vertical with Confidence.®